Tuesday, May 15, 2007

A Hole


We learned this week that the entire property is rock. All of it. A big thanks to Walter for surviving a full week of hammering. Above is the massive hole for the foundation, with a tiny Nina peering over the edge. The near end of the hole will be our garage, and the far end will be the full basement. The dirt to the left will be terraced up to our rear patio. To the right of the hole will be the stairs to the front door. Here's another view of the hole...


In some ways, having all that rock was a blessing. The driveway that was in place when we purchased the lot stopped well short of the garage. We were able to use the excavated shale for the driveway extension. See below...


This is looking across the new portion of the driveway. The house will sit on top of the hill on the other side of the driveway.

It wasn't just the house site that needed hammering. Check out these pictures of the electric/phone/cable trench. It runs through the section of the property that's all pine trees, then follows the driveway up toward the house.


We also hammered out trenches for the septic lines and another big hole for the septic tank. A lot was accomplished last week.

Well, that's about it for this installment of Bill + Nina's Excellent Adventure. We're hopeful that we'll see a lot more progress this week. Walter's trying to get all the septic pipes, electric and phone cables, and conduits layed this week so he can close up the trenches. What's even more exciting is that he'll be placing the forms that will be used for the foundation. Our local architect will hopefully meet us on site this weekend to give his approval. It's possible that we could have our foundation in less than two weeks!

Thanks for reading. See you soon.

Tuesday, May 08, 2007

progress

hi. here's the hole in the ground as it looked on saturday. walter's breaking out the hammer this week, so next week this photo will look drastically different.

below is a pan of our future backyard and pool area. walter has been gradually thinning out the small trees and underbrush, exposing the rocks and moss that give the property its character. have a look...



stack o wood below.

that's all for now.

Sunday, April 15, 2007

groundbreaking

When we went up to check on progress this past Saturday, we arrived to find the beginnings of a giant hole in the ground. The photo above is taken from the same vantage as the first photo of last week's post, and from now on, this will be my weekly photo spot from which we'll be able to mark our progress. I am trying my best to mark the corners of the house, as it is really difficult to gauge from the photo. Billy + Walter are standing at the southwest corner, and the big orange piece of equipment is pretty much at the northwest corner. The right side of the photo shows the backyard area where the pool will eventually go. Whenever that might happen. Here's a view of everything as you come up the driveway:

Below is a photo taken from the southwest corner looking east.

As the trees get thinned out, a lot of the shale outcroppings are being exposed, and they look amazing. Hopefully all the moss will be able to survive after the trees are gone (moss thrives in the shade). The big dirt hole above is a good sign - that means no rock and therefore no expensive laborious hammering required for excavation...in that spot. Walter did hit some rock on the west side of the home site, but so far he thinks it's shale and will therefore crumble pretty easily. The good news is that we only need full basement space enough for our mechanicals (which won't be a problem to get), and so, if there is too much rock as the excavation moves north, we'll just make the rest of the basement a crawl space.

We'll be in London this week, and therefore won't be up to visit the site on Saturday, so check back the first week of May for more progress, when hopefully there will be a more recognizable building-shaped hole in the ground.

Tuesday, April 10, 2007

HURRICANE WALTER!

Despite what you see above, there was no actual hurricane. Last week, our G.C. (general contractor), Walter Heitmann (above), officially began work on our site. We had met with him previously to go through and mark which trees go, and which stay. The above photo was taken looking at the home site, looking northwest. Clearing is a delicate process because once you cut a tree down, you can't put it back. Obviously we'll need to clear the immediate area around the footprint of the house. As for the surrounding area, we don't want some huge artificial clearing, but we'd like to clear enough so that 1) trees don't one day fall on our house, and 2) we have enough sunlight shining into the house and on the yard area. So we are doing this in stages. When we went up on Saturday, we marked some more as keepers, and some as gone-ers (I don't know how to spell that). This week, Walter and his team will be chipping up all of the smaller felled trees and brush, and putting aside the larger ones to dry so we can make furniture out of them - we have mostly white oak and pine, and i think some hemlock? So, this will be the process until we are happy with the rough landscape - clear enough for the house and yard area, then gradually thinning out the surrounding land. Hopefully in another week or two, we can start excavating! Here are some more pictures - click on them to enlarge:


Tuesday, March 06, 2007

Updated 3D Model


Nina and I updated our 3D model, and we're thrilled with the result. Our color palette consists of four surfaces:
  • Red cedar, stained black - siding
  • Red cedar, with a clear finish - garage doors, front door, covered deck floor and ceiling, and front planter
  • Aluminum/Steel - roof, windows, and cable rail around the deck
  • Poured concrete - foundation

Click the image for a larger version.

Monday, March 05, 2007

Updated Plans

Our plans have changed somewhat since they were posted back in November. We've moved the entrance to the garage, removed the wraparound deck, and made some minor adjustments to the framing to account for the shear walls that are required by code.

Check out the updated plans below, and stay tuned for some exciting 3D images this afternoon...

Garage/Basement

1st Floor

2nd Floor

Monday, January 22, 2007

fireplace

hi. i just haven't posted in a while, so i thought i'd post this elevation in our main space. it shows our groovy fireplace.

Monday, December 18, 2006

haus

Here is the view of our house looking southeast. I am finally fiddling around with a 3D modeling program called Rhinoceros, which is what was used to create what you see above. As you saw from our plans, we would enter the house from inside the garage, but a guest could just park in front of the garage, climb the steps you see beside it, and enter through the front door. They're really not going to be white, I just haven't finished the model yet. The land is also not so grassy, and there are tons of trees everywhere. So just look at this as a basic collage of sorts - I'm still figuring out the quirks. Here are some more views:

This is just around the corner from the first view - looking southeast. The porch above the garage allows you to either enter the front door, or just come around the back to our yard area, which won't really be a yard, just a rough play landscape, hopefully with a pool.

This is the view northeast. I'll keep working on the interior of the model, and post those later.

Friday, November 17, 2006

Approved!

On Wednesday night, Nina and I received final approval from the Stanford Planning Board for the relocation of our development envelope. Simply put, this approval will allow us to place the house in a better location on the site. Yesterday, we got Board of Health approval for the revision and filed the new drawings with the County Clerk's office, concluding a process that began about six months ago. This is the map we filed, with a closeup of our copy of the signed approval from the planning board chairman.

As our drawings were being accepted by the County Clerk, the radio in the office started playing "Celebration" by Kool & The Gang. Kinda funny.

Nina and I are diligently working on finishing drawings and specifications, and once they are complete, we'll be sending them out to contractors to get bids. We'll post some more images soon.

Monday, November 13, 2006

drawrings

so, finally, here are some drawings of our new house. for a while we had two buildings joined by a bridge, as we have shown some of you. this layout had a few quirks that we decided to resolve by a full-on redesign. now it's one long dramatic volume, which we feel will be more energy-efficient, and will as well be easier (read: less $$$) to build. it has changed what feels like a million times, but i think we are set on this one. that is, until we get our pricing back.


above is the ground floor. you can either enter from the garage, or, if you park outside, you can climb the stairs and enter through the front door above the garage, which is shown in the first floor plan below. the south end of the house sits on a hill, so only a small chunk of land will need to be excavated for a foundation. the land slopes downward (hence the need for stairs to climb up to the main level) so we can have a full basement without needing to do too much site work.

above is the first floor, which is flush with the ground level to the east (where the patio + pool are) so, as you see, the garage is bumped out enough to form a path to take you to the front door. you enter through the mudroom (labled on the plan - click to enlarge) where you hang up your coat, hat, shoes, etc. on the north end, is the tv room / playroom. we didn't want to have a tv in the main space, but wanted to have one to watch dvds, so we relegated it to the north end of the house. this will also have a pull-out couch in case we have a lot of guests, and can be closed off by those large doors / partitions you see in front of the mudroom cubbies. the main space consists of the kitchen, dining room, and living room with a gas fireplace (on the south wall) and is one big open area. outside, there is a patio for grillin' and outdoor dining, and a pool out in what will become a kind of yard area. beyond that (not shown) will be a firepit. and scattered through the property will be the miniature golf holes, yoga pavilion, and ski jump, as some of you have already requested.


this is the second floor, which has two guest bedrooms, a guest bathroom, the laundry closet, and the master bedroom + bath. pretty self-explanatory. at the north end is our rainy summer day hangout area. this is an outdoor porch with a roof.


















this is the front elevation. most of these windows will be operable awnings for cross-ventilation. as i said earlier, the south end (on the right) is at the top of a rocky hill, which slopes north (toward the garage), so under the house, to the right of the garage will be (if we can preserve them) the existing outcroppings of mossy shale. not sure if you can see the lines on the drawing, but we'll be hopefully using reclaimed barn siding to clad the house, and if that proves too cost prohibitive, we'll be going with yellow cedar. the roof is a standing-seam metal roof, and the garage will be poured concrete, like the rest of the foundation, and we may try to clad the garage door in cor-ten steel (fast-rusting steel), but this is still up for discussion. we're also going to try to run ivy or some other climbing plant up the exposed sides of the garage.

this is our back elevation. this is what you'd see from the patio, the pool, the outdoor hangout areas. this faces east, so the sun will creep right through those top floor windows into the bedrooms as soon as it rises, summoning everyone to enjoy the great outdoors. that is why you'd be there, isn't it?

there are a few things up for discussion on the north and south elevations, so they are not done yet. but as soon as they are, i'll post some 3d renderings i'm currently putting together so y'all have a better idea about what this thing will look like on the site, with its actual materials.

also, check out some of our new photos.